Tools - EVM Formulas
14:33
Posted by jason tratch
| 
EVM
  (earned value management) is often discussed but often not understood. 
EVM combines
  the management of scope, schedule, and cost into an analytical set of
  formulas.  EVM can play a crucial role in answering management
  questions that are critical to the success of the project, such as: 
 
If the
  project EVM results show that the project is behind schedule or over budget,
  the project manager can use the EVM methodology to help identify: 
 
Organizations
  have such confidence in the EVM method that they require it as mandatory
  trending and reporting starting as soon as the project has resources.  The
  attraction to the use of the earned value is that it provides accurate
  measurements of performance as early as 15 percent into the project.  With
  an accurate “early warning” signal, actions can be taken by a project manager
  to avoid final cost and schedule over runs. 
Earned
  value management involves calculating three independent yet related
  variables.  These include: 
·         Planned Value (PV) - describes how
  far along a project is supposed to be at any given point in the project
  schedule. It is a numeric reflection of the budgeted work that is scheduled
  to be performed, and it is the established baseline (also known as the performance
  measurement baseline) against which the actual progress of the project is
  measured. Once it is established, this baseline may change only to reflect
  cost and schedule changes necessitated by changes in the scope of work. PV is
  also known as the Budgeted Cost for Work Scheduled (BCWS). 
·         Earned Value (EV) is a snapshot of
  a project at a given point in time that reflects the amount of work that has
  actually been accomplished, expressed as the planned value for that
  work.  EV is also known as the Budgeted Cost for Work Performed
  (BCWP). 
·         Actual Cost (AC) is an indication
  of the level of resources that have been expended to achieve the actual work
  performed to date or in a time period.  AC is also known as the
  Actual Cost of Work Performed (ACWP). 
EVM (earned value management) formulas include: 
Earned
  value if not provided: 
 
Schedule
  variance and cost variance can be calculated by: 
·         SV = EV – PV 
·         CV = EV – AC 
Note: negatives are unfavourable, positives are
  favourable 
Variance
  at completion can be calculated by: 
·         VAC = BAC – EAC (budget at completion
  – estimate at completion) 
Note: negatives are unfavourable, positives are
  favourable 
Schedule
  performance index and cost performance index can be measured by: 
 
Note: if SPI > 1 this is good (ahead of schedule)
  or < 1 behind schedule, if CPI is > 1 this is good (under budget) or
  < 1 over budget 
Estimate
  at completion can be measured by: 
Note:  ETC
  is estimate to complete, BAC is budget at completion) 
 
variances
  will follow similar trend to date, future performance will be the same as all
  past performance 
 
Future cost
  performance will be the same as the last three measurement periods (i, j, k) 
 
Future cost
  performance will be influenced additionally by past schedule performance 
 
Future cost
  performance will be influenced jointly in some proportion by both indices 
Emerging
  EVM practice formulas: 
 
Note:  this method gives another
  perspective for projects that run over schedule and do not want only a work
  based method to evaluate schedule 
IF this
  all sounds complicated, it is because it can be.  So until you start to feel
  comfortable, do not over do it.  Stick to accounting basics. 
Understand
  what your stakeholders need to know (ask them if unsure) and understand what
  you need to know and report on. 
At a
  minimum, any point in time you must have in your back pocket, info that can
  be communicated related to (and ensure the entire team knows this): 
Schedule 
1 - are you ahead or behind schedule 
2
  - what percentage are you ahead or behind schedule 
3
  - what was original and new estimated end date 
Budget 
1 - are you ahead or behind in budget 
2 - what percentage are
  you ahead or behind in budget 
3
  - what was original and new estimated budget 
For more
  information regarding EVM methodology, you can refer to the Practice Standard
  for Earned Value Management (2nd Ed.), published by the Project Management
  Institute (PMI).  
Also, the
  two links listed below provide more details and understanding related to the
  EVM methodologies. You will find a deeper level of detail and examples. | 
		This entry was posted on October 4, 2009 at 12:14 pm, and is filed under       
		
Share,
Tools
. Follow any responses to this post through RSS. You can leave a response, or trackback from your own site.                                    
		
Subscribe to:
Post Comments (Atom)
 
 
30 March 2020 at 20:56
Au moment où j'ai ouvert la boîte, acheter des montres de luxe à bas prix j'ai été surpris qu'il ne s'agisse que d'une réplique, mais elle avait exactement le même aspect que l'original et la qualité était bonne. Je pense que cela devrait être la meilleure réplique de montre que j'ai jamais achetée. Je partage ce site avec mes amis.acheter pas cher rolex day-date les montres Ils sont très heureux, le prix est bon marché, je peux acheter une telle montre.